Wednesday 23 January 2013

Chapter 4: Project Management and Planning




True-False Questions

1.       A steering committee is likely to bring a more diverse perspective than user groups, development teams, or top management when it comes to selecting systems development projects.

Answer:    True                 Page Reference:  95                           Difficulty:  Moderate


2.       A project initiative stemming from a business unit or an IS development group is considered to have a bottom-up source.

Answer:    True                 Page Reference:  95                           Difficulty:  Moderate


3.       Value chain analysis is concerned with determining the extent to which a project contributes to the strategic objectives of the organization.

Answer:    False                Page Reference:  96                           Difficulty:  Moderate


4.       An accept, reject, or delay decision is an input to the project selection process.

Answer:    False                Page Reference:  96                           Difficulty:  Moderate


5.       All feasibility assessment efforts will be completed before the project identification and selection decisions are made.

Answer:    False                Page Reference:  97                           Difficulty:  Moderate


6.       A project’s BPP is usually NOT shared with customers.

Answer:    True                 Page Reference:  100                          Difficulty:  Moderate


7.       Identifying and assessing project risk is an activity normally completed during project initiation.

Answer:    False                Page Reference:  100                          Difficulty:  Moderate


8.       The report that provides justification for an information systems project is called a business case.

Answer:    True                 Page Reference:  100                          Difficulty:  Easy

9.       An project charter is considerably less detailed than a BPP.

Answer:    True                 Page Reference:  100                          Difficulty:  Moderate


10.   Cost-benefit analysis is a type of operational feasibility assessment.

Answer:    False                Page Reference:  104                          Difficulty:  Moderate


11.   Increasing employee morale is a tangible benefit that can accrue from a well-developed information system.

Answer:    False                Page Reference:  105                          Difficulty:  Moderate


12.   When taking into account the time value of money, a lump sum payment up front may be as valuable as a series of installment payments that add up to a greater number of dollars than the lump sum payment.

Answer:    True                 Page Reference:  107                          Difficulty:  Moderate


13.   If you will receive $1000 from a customer in a future payment, then the present value of that payment is more than $1000.

Answer:    False                Page Reference:  107-108                   Difficulty:  Moderate


14.   Calculating a net present value requires knowledge of a discount rate.

Answer:    True                 Page Reference:  107-108                   Difficulty:  Moderate


15.   Project risk assessment is typically conducted as part of the technical feasibility analysis.

Answer:    True                 Page Reference:  110                          Difficulty:  Moderate


16.   Identification of stakeholders’ concerns and the likelihood of acceptance or rejection of a new information system is the main task in political feasibility assessment.

Answer:          True                 Page Reference:  112                          Difficulty:  Easy


17.   A project charter between a consulting firm and a client company is likely to be more formal and contractual than a project scope statement between an internal development group and a user group within the same company.

Answer:    True                 Page Reference:  115                          Difficulty:  Moderate

18.   A statement of project scope is an integral part of a baseline project plan’s introduction section.

Answer:    True                 Page Reference:  113                          Difficulty:  Easy


19.   A structured walkthrough should be conducted before the baseline plan is developed.

Answer:    False                Page Reference:  117                          Difficulty:  Moderate


20.   The incremental commitment approach typically bases decisions on whether to continue a project on the results of a structured walkthrough.

Answer:    True                 Page Reference:  121                          Difficulty:  Moderate



Multiple-Choice Questions


21.   Which individual or group is likely to focus mostly on integration with existing systems when selecting a systems development project?

a.       Top management
b.       Steering committee
c.       User department
d.       Development group

Answer: d                          Page Reference:  95                           Difficulty:  Moderate


22.   Value chain analysis is a common procedure used for:

a.       ranking and classifying potential systems projects.
b.       constructing a baseline project plan.
c.       comparing present cash outlays to future expected returns.
d.       assessing the technical feasibility of the project.

Answer: a                          Page Reference:  95-96                                   Difficulty:  Moderate




23.   The systems analysis strategy in which the project is reviewed after each stage in order to decide whether or not to continue work on the project is called:

a.       committee steering.
b.       incremental commitment.
c.       value-chain analysis.
d.       feasibility assessment.

Answer: b                          Page Reference:  97                           Difficulty:  Moderate


24.   The common rule of thumb is that ____________ percent of the total project development effort should be expended on project planning and management.

a.       1-2
b.       5-8.
c.       10-20.
d.       25-40.

Answer: c                          Page Reference:  97                           Difficulty:  Moderate


25.   The systems analyst uses communication skills and inputs from the proposed system’s customers and the technical staff to translate a vague request into a:

a.       tangible project description.
b.       return on investment.
c.       cross-functional system view.
d.       structured system walkthrough.

Answer: a                          Page Reference:  98                           Difficulty:  Moderate


26.   The business case is a document that describes the:

a.       detailed breakdown and sequence of project activities.
b.       descriptions of project deliverables for the customer.
c.       justification, benefits, and feasibility of the project.
d.       user’s problem and request for a new system.

Answer: c                          Page Reference:  100                          Difficulty:  Moderate




27.   The ____________ is a detailed, internal document created for the development team during project initiation and planning, and continuously revised during execution of the project.

a.       Project Charter
b.       System Service Request
c.       Walkthrough Review Form
d.       Baseline Project Plan

Answer: d                          Page Reference:  100-101                   Difficulty:  Moderate


28.   Which of the following would be considered a tangible benefit justifying a systems development project?

a.       Reduction of transaction costs
b.       Increased organizational flexibility
c.       Data/system conversion effort
d.       Price of new hardware leases

Answer: a                          Page Reference:  104                          Difficulty:  Moderate


29.   Monetary outlays required for maintaining the application software is considered to be a type of:

a.       intangible cost.
b.       one-time benefit.
c.       tangible benefit.
d.       recurring cost.

Answer: d                          Page Reference:  105                          Difficulty:  Moderate


30.   Suppose you are considering investing a lump sum of money at 10% annual interest rate and will collect a total of $1000 after three years. What is the approximate present value for this investment?

a.       approximately $500
b.       approximately $675
c.       approximately $750
d.       approximately $825

Answer: c                          Page Reference:  107-108                   Difficulty:  Hard



31.   The yearly NPV cash flow is $10,000. The overall NPV cash flow is $5000. What is the break-even ratio?

a.       0.3
b.       0.5
c.       0.7
d.       0.9

Answer: b                          Page Reference:  109                          Difficulty:  Moderate


32.   Which of the following is a financial technique contributing to cost-benefit analysis?

a.       Economic feasibility
b.       Net present value
c.       Risk assessment
d.       Project scope calculation

Answer: b                          Page Reference:  109                          Difficulty:  Moderate


33.   The ratio of the net cash receipts of a project divided by its cash outlays is called:

a.       time value of money.
b.       net present value.
c.       break-even analysis.
d.       return on investment.

Answer: d                          Page Reference:  109                          Difficulty:  Moderate


34.   Issues such as project size, ease of requirements attainment, degree of standardization, and developer expertise all should be considered when performing:

a.       operational feasibility evaluation.
b.       cost-benefit analysis.
c.       technical risk assessment.
d.       political feasibility studies.

Answer: c                          Page Reference:  110-111                   Difficulty:  Moderate


35.   Of the following scenarios, which implies the greatest risk for a project?

a.       High familiarity with application area, high structure, small project
b.       Low familiarity with application area, low structure, large project
c.       High familiarity with application area, low structure, small project
d.       Low familiarity with application area, high structure, large project

Answer: b                          Page Reference:  111-112                   Difficulty:  Moderate
36.   The baseline project plan’s ____________ section should include a comparison of the alternative system configurations along with a narrative of the recommended solution.

a.       Introduction
b.       system description
c.       feasibility assessment
d.       configuration section

Answer: b                          Page Reference:  114                          Difficulty:  Moderate


37.   The primary intended audience for the Project Scope Statement document is the:

a.       project manager.
b.       customer.
c.       development team.
d.       steering committee.

Answer: b                          Page Reference:  115                          Difficulty:  Moderate


38.   Gantt or network charts displaying the overall project schedule should be placed in the baseline project plan’s ____________ section.

a.       introduction
b.       system description
c.       feasibility assessment
d.       management issues

Answer: c                          Page Reference:  116                          Difficulty:  Moderate


39.   Team configurations and communications plans are part of the baseline project plan’s ____________ section.

a.       introduction
b.       system description
c.       feasibility assessment
d.       management issues

Answer: d                          Page Reference:  116-117                   Difficulty:  Moderate


40.   A peer group review of a product created during the systems development process is called a:

a.       structured walkthrough.
b.       feasibility study.
c.       methodology review.
d.       peer group overview.

Answer: a                          Page Reference:  117                          Difficulty:  Moderate



Essay and Problem-Solving Questions

41.   Compare and contrast the four most common stakeholder groups that are involved in identifying and selecting potential information systems development projects. For each group identified, what is the focus that the group brings to bear in its selection decision, and what are the characteristics of the project with respect to cost, duration, complexity and system size? Which of these approaches are considered to be top-down, and which are bottom-up?

Answer:

The process of identifying and selecting information systems for development is typically initiated by one of four possible constituencies: top management, an IS steering committee, an individual user group or department, or members of the IS staff. Top management tends to have a strategic focus, aligning the system directly to organizational goals and objectives. Projects initiated by top management tend to be very large, highly complex, extend over long durations, and quite costly. A steering committee has a cross-functional focus, bringing to bear opinions and insights from a diverse range of personnel. These systems are also large and complex requiring long, costly project commitment, although typically not as much as the projects initiated by top management. User departments tend to have a much narrower and tactical focus, and the development efforts required for meeting their needs are typically less expensive and involve shorter duration, resulting in simpler and smaller systems. The IS development group’s primary focus is technical, specifically related to integration of the new system with existing systems used by the organization. Their efforts range from low to high in cost, complexity, duration and size. Top-down approaches are those initiated by top management or the steering committee, whereas those initiated by a user department or the IS staff are considered bottom-up.

Page Reference:  93-95                                   Difficulty:  Moderate


42.   List and describe the criteria commonly used to evaluate and rank potential information systems development projects. As you describe each criterion, relate it to its analogous feasibility analyses that will be performed during project planning.

Answer:

The most commonly used evaluation criteria pertain to value chain, strategic alignment, potential benefits, resource availability, project size and duration, and technical difficulty and risk. Value chain analysis examines the extent to which the project activities add value or cost to the organization; this is analogous to economic feasibility and in particular cost-benefit analysis. Strategic alignment refers to the extent to which a project is viewed as helping the organization achieve its goals and objectives, and is analogous to political, operational, and perhaps legal feasibility analysis. Potential benefits measuring the extent to which the project is perceived to improve profits, customer service, etc., and is analogous to economic feasibility and cost-benefit analysis. Resource availability is an assessment of whether the amount and type of resources is available to the organization; this is relevant for both schedule and technical feasibility. Project size and duration addresses how long the project is expected to take, and is related to schedule feasibility. The technical difficulty and risk criterion is, of course, most directly tied to technical feasibility and risk assessment.

Page Reference:  95-96,                      Difficulty:  Moderate


43.   List and describe the different types of feasibility considered during a feasibility analysis, and identify techniques and/or considerations involved in each of these types of feasibility assessment.

Answer:

Feasibility analysis involves assessing likelihood of project success with regard to economic, operational, technical, schedule, legal and political factors. Economic feasibility assessment involves performing a cost-benefit analysis identifying both tangible and intangible costs and benefits. Common techniques for the tangible cost and benefit examinations include net present value, return on investment, and break-even analyses. Operational feasibility analysis assesses the likelihood that the proposed system will solve the problems that motivate the project in the first place, and requires a clear understanding of how the information system will fit into the current day-to-day operations of the organization. Technical feasibility addresses the question of whether the proposed system can be successfully constructed given the organization’s current technological status. This involves identifying potential technical risks related to project size, ease of requirements attainment, type of technology required, and the technical expertise of the development staff. Schedule feasibility considers the likelihood that a project can be completed in a timely manner based on knowledge of the required project deadlines and milestones. Legal feasibility examines the effect on the project and system of regulatory constraints and requirements, such as copyright issues, foreign trade restrictions, labor laws, and contractual issues. Finally, political feasibility examines the degree to which the new system will be welcomed or resisted by personnel in the organization.

Page Reference:  102-112                   Difficulty:  Moderate


44.   When performing a cost-benefit analysis, it is important to consider the tangible and intangible benefits, the tangible and intangible costs, and to recognize the difference between one-time and recurring costs. Briefly define each of these terms and give examples that you think would be typical for systems development projects.

Answer:

The term “tangible” refers to costs or benefits that can be directly measured in dollars and cents, whereas “intangible” means costs and benefits that have no direct monetary translation. With this in mind, tangible benefits from a new information system include items such as transaction cost reduction, error reduction, increased operational speed, and increased sales opportunities. Intangible benefits include organizational flexibility, employee morale, improved customer relations, and promotion of organizational learning and understanding. Tangible costs include hardware, labor, and operational costs, whereas intangible costs include political resistance, operational inefficiencies, and loss of employee morale. One-time costs are those involved in project initiation, systems development, and the start-up of the system, and include development costs, new hardware and software purchases, site preparation, system conversion, installation and user training. Recurring costs exist for the ongoing life and use of the system, and include application maintenance, incremental data storage and communications costs, new hardware and software leases, and consumable supplies.

Page Reference:  104-107                   Difficulty:  Moderate


45.   Identify three common financial techniques for conducting economic feasibility, particularly as it relates to analyzing tangible costs and benefits. Also, discuss time value of money and how this relates to the economic feasibility assessment. Be sure to include in this discussion the names of the three techniques, a description of their mathematical formulas, a discussion of what information each provides, and an identification of which techniques rely on outputs from which others.

Answer:

The three techniques are called net present value (NPV), return on investment (ROI), and break-even analysis (BEA). NPV is the starting point on which both ROI and BEA depend. NPV is directly related to time value of money (TVM), which compares present cash outlays to future expected returns based on an expected discount rate. The NPV is calculated by combining present values (PV) for each year. The PV uses the discount rate in this formula: PVn =  Y * (1/ (1 + i) n)   where Y is the monetary amount in today’s dollars, i is the discount rate, and n is the number of years for realization of the investment or loan. NPV is a sum of all PVs for the duration of the loan or investment. The NPV is used to determine the present value of both costs and benefits of a system.

Based on NPVs for the costs and benefits, you can calculate ROI, which is the ratio of net cash receipts divided by cash outlays. In other mathematical terms, ROI = (NPVbenefits – NPVcosts) / NPVcosts.  ROI is a useful number for comparing the value of different alternative projects in order to select the most cost-effective solution. In essence, the ROI gives an idea of the degree of profitability you can expect at the end of the project time horizon.

The BEA is also calculated using PV and NPV results. BEA determines the amount of time required for the cumulative cash inflow from a project to equal its initial and ongoing costs. To determine this, you calculate PV and NPV costs and benefits for each year of the project until you reach a year where the NPV benefits are higher than the NPV costs. At this point, you can obtain the specific point in time of the year in question by calculating that year’s break-even ratio. The break-even ratio is calculated by subtracting the overall NPV cash flow at that year from one-year cash flow for that year, and then dividing the result by the one-year sash flow for that year. In mathematical terms, it looks like this: Break-even ratio =  ((PVbenefits – PVcosts) – (NPVbenefits – NPVcosts))  /   (PVbenefits – PVcosts).

That ratio, when added to the previous year number, gives the total number of years to the break-even point. In essence, the break-even analysis gives you an idea of how long it takes before you begin to turn a profit for the project efforts.

Page Reference:  106-110                   Difficulty:  Hard


46.   Consider the following scenario of tangible costs and benefits for a systems development project. Estimated development time is one year, and the one-time development cost is $9000. Each year after that, maintenance and usage costs are $4000. The estimated benefits after the system is developed are $8000 per year. Note that these estimates are based on today’s dollar values. Assume a discount rate of 10% per year on the time value of money.

Based on the above scenario, calculate the net present value for benefits and costs over a five year time horizon (calculate NPV for each year). Then determine the return on investment after this time period. Finally, determine the break-even point. Show your work.


Answer:

NPV Costs:
Year 0: $9000  (one-time development cost)
Year 1:  9000 + 4000 * (1/ (1 + .1) 1) = 9000 + 3636 = $12,636
Year 2:  12,636 + 4000 * (1/ (1 + .1) 2) = 12,636 + 3306 = $15,942
Year 3:  15942 + 4000 * (1/ (1 + .1) 3) = 15942 + 3005 =  $18,947
Year 4:  $21,679
Year 5:  $24,163

NPV Benefits
      Year 0:  $0
      Year 1:  8000 * (1/ (1 + .1) 1) = $7273
      Year 2:  7273 + 8000 * (1/ (1 + .1) 2) = 7273 + 6612 = $13,884
      Year 3:  13884 + 8000 * (1/ (1 + .1) 3) = 13884 + 6011 = $19,895
      Year 4:  $25,359
      Year 5:  $30,326

Overall NPV:  $6163
ROI:   6163/24163 = 25.5%

Break-Even between year 2 and 3.

Break-Even Ratio (year 3):   ((6011 – 3005) – (19895 – 18947))  /   (6011 – 3005) =
(3006 – 948)/3006 = 0.685

Break-even point is year 2.685


Page Reference:  106-110                   Difficulty:  Hard


47.   Discuss the project risk factors that a project manager must be concerned with when planning the project. How do these factors influence the likelihood of project success? At which point in the planning process are these factors evaluated? What are some consequences of neglecting to address these risk factors?

Answer:

Project risk is most directly affected by (a) the size and scope of the project, (b) the level of structure of the requirements process, (c) the degree of standardization of the technology involved, and (d) the level of familiarity and expertise of the technical staff and user community. As a general rule of thumb, large projects are riskier than small projects, low structure is riskier than high structure, low standardization is riskier than high standardization, and low familiarity is riskier than high familiarity.  Projects will vary in each of these factors, so it is important that the project manager carefully assess each of these factors; this is typically done as part of the feasibility assessment. If project risk factors are not considered during the planning process, this could lead to inaccurate cost and duration estimates, or a poorly developed system that does not meet performance and integration requirements. In sum, the project will be less likely to attain its desired benefits.

Page Reference:  110-111                   Difficulty:  Moderate


48.   Describe the structure of a baseline project plan as discussed in Chapter 4. List all the sections, indicate their purposes, and briefly describe the contents of each section.

Answer:

The baseline project plan consists of an introduction, a systems description, a feasibility analysis, and a discussion of management-related issues. The introduction’s purpose is to provide an overview of the entire plan document, and to succinctly state the recommended course of action. The purpose of the system description section is to provide a detailed discussion of the alternative system solutions and a justification for the selected one. The feasibility assessment is supposed to outline the costs, benefits, and risks involved in the project, and to outline the tasks and schedule required for completing the project. The management issues section outlines management concerns, particularly with respect to unique characteristics that are not shared with other projects.
The introduction is composed of a project overview, including a statement of the problem, project scope, and a statement of feasibility. In addition, the recommendation is briefly described. The system description section presents each alternative solution, and then discusses the recommended solution, together with required inputs, outputs, configuration, processes and tasks. The feasibility assessment includes economic, technical, operational, legal/contractual, and political analyses. In addition, Gantt, network, PERT, WBS, and resource allocation analyses are presented to indicate schedule feasibility. Management issues include discussions of team configuration, a communication plan, project standards and procedures, and any other relevant issues pertaining to the management of the project.

Page Reference:  113-117                   Difficulty:  Moderate


49.   What is a project scope statement (PSS)? Who are the intended audience of a PSS, and what purpose does it serve? How does the PSS relate to the baseline project plan?  How does the PSS affect the relationship between the systems developers and the customer?

Answer:

The project scope statement is a short document, prepared primarily for the customer. The PSS outlines the objectives and constraints for the project. It is basically a high-level description of the baseline project plan. Specifically, it describes what the project will deliver, and the work that is required to complete the project. Therefore, the PSS is a useful communication tool which ensures that the developers and the customer have a common understanding of the project size, duration, and outcome. The PSS may serve as a formal contract between developer and customer, or may simply be an informal communication vehicle, depending on the nature of the relationship.

Page Reference:  115              Difficulty:  Moderate



50.   What is a structured walkthrough? What purpose does it serve in the planning process? Which work products in a systems project can benefit from a walkthrough? How is the walkthrough process implemented? List and describe the participant roles involved in a typical walkthrough.

Answer:

A structured walkthrough is a peer group review of any product created during the systems development process. The purpose is to assure that the system conforms to organizational standards and that all stakeholders have a common understanding and agreement regarding the product being reviewed. Walkthroughs are useful for assessing the deliverables from each phase of the systems development process, including the baseline project plan, system specifications, logical and physical designs, code and program segments, test procedures and results, and manuals and documentation.

A walkthrough typically takes place as one or more meetings attended by different stakeholder representatives. The work product is presented, and then stakeholders are polled to see if they have any recommendations for improvement. Typical roles include (1) a coordinator who plans the meeting and facilitates discussion, (2) a presenter who describes the work product to the group, (3) a user representative who evaluates the product based on the customer perspective, (4) a secretary to keep notes on the meeting, (5) a standard-bearer who ensures that technical standards are being satisfied, and (6) a maintenance oracle who evaluates the product with the goal of making maintenance as easy as possible.

Page Reference:  117-119                   Difficulty:  Moderate 

True-False Questions

1.       A steering committee is likely to bring a more diverse perspective than user groups, development teams, or top management when it comes to selecting systems development projects.

Answer:    True                 Page Reference:  95                           Difficulty:  Moderate


2.       A project initiative stemming from a business unit or an IS development group is considered to have a bottom-up source.

Answer:    True                 Page Reference:  95                           Difficulty:  Moderate


3.       Value chain analysis is concerned with determining the extent to which a project contributes to the strategic objectives of the organization.

Answer:    False                Page Reference:  96                           Difficulty:  Moderate


4.       An accept, reject, or delay decision is an input to the project selection process.

Answer:    False                Page Reference:  96                           Difficulty:  Moderate


5.       All feasibility assessment efforts will be completed before the project identification and selection decisions are made.

Answer:    False                Page Reference:  97                           Difficulty:  Moderate


6.       A project’s BPP is usually NOT shared with customers.

Answer:    True                 Page Reference:  100                          Difficulty:  Moderate


7.       Identifying and assessing project risk is an activity normally completed during project initiation.

Answer:    False                Page Reference:  100                          Difficulty:  Moderate


8.       The report that provides justification for an information systems project is called a business case.

Answer:    True                 Page Reference:  100                          Difficulty:  Easy

9.       An project charter is considerably less detailed than a BPP.

Answer:    True                 Page Reference:  100                          Difficulty:  Moderate


10.   Cost-benefit analysis is a type of operational feasibility assessment.

Answer:    False                Page Reference:  104                          Difficulty:  Moderate


11.   Increasing employee morale is a tangible benefit that can accrue from a well-developed information system.

Answer:    False                Page Reference:  105                          Difficulty:  Moderate


12.   When taking into account the time value of money, a lump sum payment up front may be as valuable as a series of installment payments that add up to a greater number of dollars than the lump sum payment.

Answer:    True                 Page Reference:  107                          Difficulty:  Moderate


13.   If you will receive $1000 from a customer in a future payment, then the present value of that payment is more than $1000.

Answer:    False                Page Reference:  107-108                   Difficulty:  Moderate


14.   Calculating a net present value requires knowledge of a discount rate.

Answer:    True                 Page Reference:  107-108                   Difficulty:  Moderate


15.   Project risk assessment is typically conducted as part of the technical feasibility analysis.

Answer:    True                 Page Reference:  110                          Difficulty:  Moderate


16.   Identification of stakeholders’ concerns and the likelihood of acceptance or rejection of a new information system is the main task in political feasibility assessment.

Answer:          True                 Page Reference:  112                          Difficulty:  Easy


17.   A project charter between a consulting firm and a client company is likely to be more formal and contractual than a project scope statement between an internal development group and a user group within the same company.

Answer:    True                 Page Reference:  115                          Difficulty:  Moderate

18.   A statement of project scope is an integral part of a baseline project plan’s introduction section.

Answer:    True                 Page Reference:  113                          Difficulty:  Easy


19.   A structured walkthrough should be conducted before the baseline plan is developed.

Answer:    False                Page Reference:  117                          Difficulty:  Moderate


20.   The incremental commitment approach typically bases decisions on whether to continue a project on the results of a structured walkthrough.

Answer:    True                 Page Reference:  121                          Difficulty:  Moderate



Multiple-Choice Questions


21.   Which individual or group is likely to focus mostly on integration with existing systems when selecting a systems development project?

a.       Top management
b.       Steering committee
c.       User department
d.       Development group

Answer: d                          Page Reference:  95                           Difficulty:  Moderate


22.   Value chain analysis is a common procedure used for:

a.       ranking and classifying potential systems projects.
b.       constructing a baseline project plan.
c.       comparing present cash outlays to future expected returns.
d.       assessing the technical feasibility of the project.

Answer: a                          Page Reference:  95-96                                   Difficulty:  Moderate




23.   The systems analysis strategy in which the project is reviewed after each stage in order to decide whether or not to continue work on the project is called:

a.       committee steering.
b.       incremental commitment.
c.       value-chain analysis.
d.       feasibility assessment.

Answer: b                          Page Reference:  97                           Difficulty:  Moderate


24.   The common rule of thumb is that ____________ percent of the total project development effort should be expended on project planning and management.

a.       1-2
b.       5-8.
c.       10-20.
d.       25-40.

Answer: c                          Page Reference:  97                           Difficulty:  Moderate


25.   The systems analyst uses communication skills and inputs from the proposed system’s customers and the technical staff to translate a vague request into a:

a.       tangible project description.
b.       return on investment.
c.       cross-functional system view.
d.       structured system walkthrough.

Answer: a                          Page Reference:  98                           Difficulty:  Moderate


26.   The business case is a document that describes the:

a.       detailed breakdown and sequence of project activities.
b.       descriptions of project deliverables for the customer.
c.       justification, benefits, and feasibility of the project.
d.       user’s problem and request for a new system.

Answer: c                          Page Reference:  100                          Difficulty:  Moderate




27.   The ____________ is a detailed, internal document created for the development team during project initiation and planning, and continuously revised during execution of the project.

a.       Project Charter
b.       System Service Request
c.       Walkthrough Review Form
d.       Baseline Project Plan

Answer: d                          Page Reference:  100-101                   Difficulty:  Moderate


28.   Which of the following would be considered a tangible benefit justifying a systems development project?

a.       Reduction of transaction costs
b.       Increased organizational flexibility
c.       Data/system conversion effort
d.       Price of new hardware leases

Answer: a                          Page Reference:  104                          Difficulty:  Moderate


29.   Monetary outlays required for maintaining the application software is considered to be a type of:

a.       intangible cost.
b.       one-time benefit.
c.       tangible benefit.
d.       recurring cost.

Answer: d                          Page Reference:  105                          Difficulty:  Moderate


30.   Suppose you are considering investing a lump sum of money at 10% annual interest rate and will collect a total of $1000 after three years. What is the approximate present value for this investment?

a.       approximately $500
b.       approximately $675
c.       approximately $750
d.       approximately $825

Answer: c                          Page Reference:  107-108                   Difficulty:  Hard



31.   The yearly NPV cash flow is $10,000. The overall NPV cash flow is $5000. What is the break-even ratio?

a.       0.3
b.       0.5
c.       0.7
d.       0.9

Answer: b                          Page Reference:  109                          Difficulty:  Moderate


32.   Which of the following is a financial technique contributing to cost-benefit analysis?

a.       Economic feasibility
b.       Net present value
c.       Risk assessment
d.       Project scope calculation

Answer: b                          Page Reference:  109                          Difficulty:  Moderate


33.   The ratio of the net cash receipts of a project divided by its cash outlays is called:

a.       time value of money.
b.       net present value.
c.       break-even analysis.
d.       return on investment.

Answer: d                          Page Reference:  109                          Difficulty:  Moderate


34.   Issues such as project size, ease of requirements attainment, degree of standardization, and developer expertise all should be considered when performing:

a.       operational feasibility evaluation.
b.       cost-benefit analysis.
c.       technical risk assessment.
d.       political feasibility studies.

Answer: c                          Page Reference:  110-111                   Difficulty:  Moderate


35.   Of the following scenarios, which implies the greatest risk for a project?

a.       High familiarity with application area, high structure, small project
b.       Low familiarity with application area, low structure, large project
c.       High familiarity with application area, low structure, small project
d.       Low familiarity with application area, high structure, large project

Answer: b                          Page Reference:  111-112                   Difficulty:  Moderate
36.   The baseline project plan’s ____________ section should include a comparison of the alternative system configurations along with a narrative of the recommended solution.

a.       Introduction
b.       system description
c.       feasibility assessment
d.       configuration section

Answer: b                          Page Reference:  114                          Difficulty:  Moderate


37.   The primary intended audience for the Project Scope Statement document is the:

a.       project manager.
b.       customer.
c.       development team.
d.       steering committee.

Answer: b                          Page Reference:  115                          Difficulty:  Moderate


38.   Gantt or network charts displaying the overall project schedule should be placed in the baseline project plan’s ____________ section.

a.       introduction
b.       system description
c.       feasibility assessment
d.       management issues

Answer: c                          Page Reference:  116                          Difficulty:  Moderate


39.   Team configurations and communications plans are part of the baseline project plan’s ____________ section.

a.       introduction
b.       system description
c.       feasibility assessment
d.       management issues

Answer: d                          Page Reference:  116-117                   Difficulty:  Moderate


40.   A peer group review of a product created during the systems development process is called a:

a.       structured walkthrough.
b.       feasibility study.
c.       methodology review.
d.       peer group overview.

Answer: a                          Page Reference:  117                          Difficulty:  Moderate



Essay and Problem-Solving Questions

41.   Compare and contrast the four most common stakeholder groups that are involved in identifying and selecting potential information systems development projects. For each group identified, what is the focus that the group brings to bear in its selection decision, and what are the characteristics of the project with respect to cost, duration, complexity and system size? Which of these approaches are considered to be top-down, and which are bottom-up?

Answer:

The process of identifying and selecting information systems for development is typically initiated by one of four possible constituencies: top management, an IS steering committee, an individual user group or department, or members of the IS staff. Top management tends to have a strategic focus, aligning the system directly to organizational goals and objectives. Projects initiated by top management tend to be very large, highly complex, extend over long durations, and quite costly. A steering committee has a cross-functional focus, bringing to bear opinions and insights from a diverse range of personnel. These systems are also large and complex requiring long, costly project commitment, although typically not as much as the projects initiated by top management. User departments tend to have a much narrower and tactical focus, and the development efforts required for meeting their needs are typically less expensive and involve shorter duration, resulting in simpler and smaller systems. The IS development group’s primary focus is technical, specifically related to integration of the new system with existing systems used by the organization. Their efforts range from low to high in cost, complexity, duration and size. Top-down approaches are those initiated by top management or the steering committee, whereas those initiated by a user department or the IS staff are considered bottom-up.

Page Reference:  93-95                                   Difficulty:  Moderate


42.   List and describe the criteria commonly used to evaluate and rank potential information systems development projects. As you describe each criterion, relate it to its analogous feasibility analyses that will be performed during project planning.

Answer:

The most commonly used evaluation criteria pertain to value chain, strategic alignment, potential benefits, resource availability, project size and duration, and technical difficulty and risk. Value chain analysis examines the extent to which the project activities add value or cost to the organization; this is analogous to economic feasibility and in particular cost-benefit analysis. Strategic alignment refers to the extent to which a project is viewed as helping the organization achieve its goals and objectives, and is analogous to political, operational, and perhaps legal feasibility analysis. Potential benefits measuring the extent to which the project is perceived to improve profits, customer service, etc., and is analogous to economic feasibility and cost-benefit analysis. Resource availability is an assessment of whether the amount and type of resources is available to the organization; this is relevant for both schedule and technical feasibility. Project size and duration addresses how long the project is expected to take, and is related to schedule feasibility. The technical difficulty and risk criterion is, of course, most directly tied to technical feasibility and risk assessment.

Page Reference:  95-96,                      Difficulty:  Moderate


43.   List and describe the different types of feasibility considered during a feasibility analysis, and identify techniques and/or considerations involved in each of these types of feasibility assessment.

Answer:

Feasibility analysis involves assessing likelihood of project success with regard to economic, operational, technical, schedule, legal and political factors. Economic feasibility assessment involves performing a cost-benefit analysis identifying both tangible and intangible costs and benefits. Common techniques for the tangible cost and benefit examinations include net present value, return on investment, and break-even analyses. Operational feasibility analysis assesses the likelihood that the proposed system will solve the problems that motivate the project in the first place, and requires a clear understanding of how the information system will fit into the current day-to-day operations of the organization. Technical feasibility addresses the question of whether the proposed system can be successfully constructed given the organization’s current technological status. This involves identifying potential technical risks related to project size, ease of requirements attainment, type of technology required, and the technical expertise of the development staff. Schedule feasibility considers the likelihood that a project can be completed in a timely manner based on knowledge of the required project deadlines and milestones. Legal feasibility examines the effect on the project and system of regulatory constraints and requirements, such as copyright issues, foreign trade restrictions, labor laws, and contractual issues. Finally, political feasibility examines the degree to which the new system will be welcomed or resisted by personnel in the organization.

Page Reference:  102-112                   Difficulty:  Moderate


44.   When performing a cost-benefit analysis, it is important to consider the tangible and intangible benefits, the tangible and intangible costs, and to recognize the difference between one-time and recurring costs. Briefly define each of these terms and give examples that you think would be typical for systems development projects.

Answer:

The term “tangible” refers to costs or benefits that can be directly measured in dollars and cents, whereas “intangible” means costs and benefits that have no direct monetary translation. With this in mind, tangible benefits from a new information system include items such as transaction cost reduction, error reduction, increased operational speed, and increased sales opportunities. Intangible benefits include organizational flexibility, employee morale, improved customer relations, and promotion of organizational learning and understanding. Tangible costs include hardware, labor, and operational costs, whereas intangible costs include political resistance, operational inefficiencies, and loss of employee morale. One-time costs are those involved in project initiation, systems development, and the start-up of the system, and include development costs, new hardware and software purchases, site preparation, system conversion, installation and user training. Recurring costs exist for the ongoing life and use of the system, and include application maintenance, incremental data storage and communications costs, new hardware and software leases, and consumable supplies.

Page Reference:  104-107                   Difficulty:  Moderate


45.   Identify three common financial techniques for conducting economic feasibility, particularly as it relates to analyzing tangible costs and benefits. Also, discuss time value of money and how this relates to the economic feasibility assessment. Be sure to include in this discussion the names of the three techniques, a description of their mathematical formulas, a discussion of what information each provides, and an identification of which techniques rely on outputs from which others.

Answer:

The three techniques are called net present value (NPV), return on investment (ROI), and break-even analysis (BEA). NPV is the starting point on which both ROI and BEA depend. NPV is directly related to time value of money (TVM), which compares present cash outlays to future expected returns based on an expected discount rate. The NPV is calculated by combining present values (PV) for each year. The PV uses the discount rate in this formula: PVn =  Y * (1/ (1 + i) n)   where Y is the monetary amount in today’s dollars, i is the discount rate, and n is the number of years for realization of the investment or loan. NPV is a sum of all PVs for the duration of the loan or investment. The NPV is used to determine the present value of both costs and benefits of a system.

Based on NPVs for the costs and benefits, you can calculate ROI, which is the ratio of net cash receipts divided by cash outlays. In other mathematical terms, ROI = (NPVbenefits – NPVcosts) / NPVcosts.  ROI is a useful number for comparing the value of different alternative projects in order to select the most cost-effective solution. In essence, the ROI gives an idea of the degree of profitability you can expect at the end of the project time horizon.

The BEA is also calculated using PV and NPV results. BEA determines the amount of time required for the cumulative cash inflow from a project to equal its initial and ongoing costs. To determine this, you calculate PV and NPV costs and benefits for each year of the project until you reach a year where the NPV benefits are higher than the NPV costs. At this point, you can obtain the specific point in time of the year in question by calculating that year’s break-even ratio. The break-even ratio is calculated by subtracting the overall NPV cash flow at that year from one-year cash flow for that year, and then dividing the result by the one-year sash flow for that year. In mathematical terms, it looks like this: Break-even ratio =  ((PVbenefits – PVcosts) – (NPVbenefits – NPVcosts))  /   (PVbenefits – PVcosts).

That ratio, when added to the previous year number, gives the total number of years to the break-even point. In essence, the break-even analysis gives you an idea of how long it takes before you begin to turn a profit for the project efforts.

Page Reference:  106-110                   Difficulty:  Hard


46.   Consider the following scenario of tangible costs and benefits for a systems development project. Estimated development time is one year, and the one-time development cost is $9000. Each year after that, maintenance and usage costs are $4000. The estimated benefits after the system is developed are $8000 per year. Note that these estimates are based on today’s dollar values. Assume a discount rate of 10% per year on the time value of money.

Based on the above scenario, calculate the net present value for benefits and costs over a five year time horizon (calculate NPV for each year). Then determine the return on investment after this time period. Finally, determine the break-even point. Show your work.


Answer:

NPV Costs:
Year 0: $9000  (one-time development cost)
Year 1:  9000 + 4000 * (1/ (1 + .1) 1) = 9000 + 3636 = $12,636
Year 2:  12,636 + 4000 * (1/ (1 + .1) 2) = 12,636 + 3306 = $15,942
Year 3:  15942 + 4000 * (1/ (1 + .1) 3) = 15942 + 3005 =  $18,947
Year 4:  $21,679
Year 5:  $24,163

NPV Benefits
      Year 0:  $0
      Year 1:  8000 * (1/ (1 + .1) 1) = $7273
      Year 2:  7273 + 8000 * (1/ (1 + .1) 2) = 7273 + 6612 = $13,884
      Year 3:  13884 + 8000 * (1/ (1 + .1) 3) = 13884 + 6011 = $19,895
      Year 4:  $25,359
      Year 5:  $30,326

Overall NPV:  $6163
ROI:   6163/24163 = 25.5%

Break-Even between year 2 and 3.

Break-Even Ratio (year 3):   ((6011 – 3005) – (19895 – 18947))  /   (6011 – 3005) =
(3006 – 948)/3006 = 0.685

Break-even point is year 2.685


Page Reference:  106-110                   Difficulty:  Hard


47.   Discuss the project risk factors that a project manager must be concerned with when planning the project. How do these factors influence the likelihood of project success? At which point in the planning process are these factors evaluated? What are some consequences of neglecting to address these risk factors?

Answer:

Project risk is most directly affected by (a) the size and scope of the project, (b) the level of structure of the requirements process, (c) the degree of standardization of the technology involved, and (d) the level of familiarity and expertise of the technical staff and user community. As a general rule of thumb, large projects are riskier than small projects, low structure is riskier than high structure, low standardization is riskier than high standardization, and low familiarity is riskier than high familiarity.  Projects will vary in each of these factors, so it is important that the project manager carefully assess each of these factors; this is typically done as part of the feasibility assessment. If project risk factors are not considered during the planning process, this could lead to inaccurate cost and duration estimates, or a poorly developed system that does not meet performance and integration requirements. In sum, the project will be less likely to attain its desired benefits.

Page Reference:  110-111                   Difficulty:  Moderate


48.   Describe the structure of a baseline project plan as discussed in Chapter 4. List all the sections, indicate their purposes, and briefly describe the contents of each section.

Answer:

The baseline project plan consists of an introduction, a systems description, a feasibility analysis, and a discussion of management-related issues. The introduction’s purpose is to provide an overview of the entire plan document, and to succinctly state the recommended course of action. The purpose of the system description section is to provide a detailed discussion of the alternative system solutions and a justification for the selected one. The feasibility assessment is supposed to outline the costs, benefits, and risks involved in the project, and to outline the tasks and schedule required for completing the project. The management issues section outlines management concerns, particularly with respect to unique characteristics that are not shared with other projects.
The introduction is composed of a project overview, including a statement of the problem, project scope, and a statement of feasibility. In addition, the recommendation is briefly described. The system description section presents each alternative solution, and then discusses the recommended solution, together with required inputs, outputs, configuration, processes and tasks. The feasibility assessment includes economic, technical, operational, legal/contractual, and political analyses. In addition, Gantt, network, PERT, WBS, and resource allocation analyses are presented to indicate schedule feasibility. Management issues include discussions of team configuration, a communication plan, project standards and procedures, and any other relevant issues pertaining to the management of the project.

Page Reference:  113-117                   Difficulty:  Moderate


49.   What is a project scope statement (PSS)? Who are the intended audience of a PSS, and what purpose does it serve? How does the PSS relate to the baseline project plan?  How does the PSS affect the relationship between the systems developers and the customer?

Answer:

The project scope statement is a short document, prepared primarily for the customer. The PSS outlines the objectives and constraints for the project. It is basically a high-level description of the baseline project plan. Specifically, it describes what the project will deliver, and the work that is required to complete the project. Therefore, the PSS is a useful communication tool which ensures that the developers and the customer have a common understanding of the project size, duration, and outcome. The PSS may serve as a formal contract between developer and customer, or may simply be an informal communication vehicle, depending on the nature of the relationship.

Page Reference:  115              Difficulty:  Moderate



50.   What is a structured walkthrough? What purpose does it serve in the planning process? Which work products in a systems project can benefit from a walkthrough? How is the walkthrough process implemented? List and describe the participant roles involved in a typical walkthrough.

Answer:

A structured walkthrough is a peer group review of any product created during the systems development process. The purpose is to assure that the system conforms to organizational standards and that all stakeholders have a common understanding and agreement regarding the product being reviewed. Walkthroughs are useful for assessing the deliverables from each phase of the systems development process, including the baseline project plan, system specifications, logical and physical designs, code and program segments, test procedures and results, and manuals and documentation.

A walkthrough typically takes place as one or more meetings attended by different stakeholder representatives. The work product is presented, and then stakeholders are polled to see if they have any recommendations for improvement. Typical roles include (1) a coordinator who plans the meeting and facilitates discussion, (2) a presenter who describes the work product to the group, (3) a user representative who evaluates the product based on the customer perspective, (4) a secretary to keep notes on the meeting, (5) a standard-bearer who ensures that technical standards are being satisfied, and (6) a maintenance oracle who evaluates the product with the goal of making maintenance as easy as possible.

Page Reference:  117-119                   Difficulty:  Moderate

No comments:

Post a Comment